
| Back to Home Page |
|
![]() |
|
||
| Late May 2008: The extension will be built where the greenhouses are currently sitting. | So the greenhouses have to go... | ||||
![]() |
|
![]() |
|||
| June 2008: The site is cleared! | |||||
![]() |
![]() |
|
|||
| The brick walls from old animal pens are revealed when the top soil is taken off. These are from when the University was a college with agricultural courses! | Brick walls are removed and the ground smooth and rolled to produce a hard flat surface. | July 2008: The holes are dug for the foundations. | |||
|
|
|
|
|||
| Concrete is poured in. | Foundation steels are erected. | The steels are clad in concrete | |||
|
|
![]() |
![]() |
|||
| Scaffolding is erected ready to lay the base for the first floor | August 2008: Shuttering is laid ready to pour the concrete floor | The concrete is poured. | |||
![]() |
![]() |
![]() |
|||
| Prefabricated stairs are lowered in by crane at the corners of the building. | An additional level of shuttering is added which will allow concrete to be poured for the roof. | September 2008: The scaffolding is taken down. This space will be laboratories in the new building. | |||
![]() |
![]() |
![]() |
|||
| Hard core is laid down and mesh is put on top ready for the base layer of concrete | The floor is laid | October 2008: Topping out ceremony held on roof | |||
|
|
![]() |
![]() |
|||
| The deputy major is presented with a 'trowel' as a memento of the occasion | November 2008: The brick and block walls are started | The internal walls are marked out on the floor. | |||
![]() |
![]() |
![]() |
|||
| Steel work is added to the roof and exterior of the building | January 2009: The supports for the internal walls go in. The offices will be to the left of the corridor and the new laboratories to the right. | ||||
![]() |
![]() |
![]() |
|||
![]() |
![]() |
![]() |
|||
| Cladding is added to the outside walls | The window frames go in | ||||
![]() |
![]() |
![]() |
|||
| The roofing starts to go on | |||||
![]() |
![]() |
![]() |
|||
| The first floor starts to be fitted out. | The plant well on the first floor | ||||
![]() |
![]() |
![]() |
|||
| The outside of the building is finished | March 2009:The laboratories start to be fitted out | ||||
![]() |
![]() |
![]() |
|||
| May 2009:The exterior of the building starts to be landscaped | |||||
![]() |
![]() |
![]() |
|||
| June 2009: The climate controlled room is commissioned ready for use | |||||
|
© National Pollen and Aerobiology Research Unit, University of Worcester, Henwick Grove, Worcester WR2 6AJ. Tel: +44 (0) 1905 855200 Fax +44 (0) 1905 855234. If you experience difficulties with this site please contact Louise Robertson |